January 1, 2016
Debt collection, Part III At completion
BY ROBERT KENNALEY
This month we complete our series of articles on debt collection with a discussion of what contractors, subcontractors and suppliers might do to protect themselves as a job moves towards completion. At this time, in particular, unpaid suppliers must be careful to consider their options and to prepare, and document, their files.
As suggested in our last article, it is extremely important to understand the notice provisions and other contractual prerequisites to a claim. If your claim is for extras or delay, your contract will often impose conditions to be met in seeking payment. While a failure to meet these conditions might not be fatal, it is better to take the issue off the table, rather providing a reason for non-payment to the other side of a dispute.
A common mistake is the failure to properly compile documentation necessary to support a claim. For example, trades who seek additional compensation as an extra under their contracts often fail to properly track the work for which they are claiming. They may invoice for time and materials, for example, without documenting the support for the amounts claimed.
Documents are key
As lawyers brought in to enforce the claim much later on, we all too often find that the backup to the claim is sorrowfully lacking. Our clients will tell us, for example, that they put two men on the extra work, for eight hours, while incurring $1,000 in material costs. Yet, by the time we have the file, the only backup to these costs are timesheets that show the men were on-site for eight hours on the day in question. By this time, of course, it is impossible for these men to actually tell us what they were doing on that day. This leaves the other side to argue that the time might have been spent on the original scope of work, or on deficiencies. Further, if the actual invoices or materials price lists are not attached to backup your claim for material costs before the job is complete, it is often extremely difficult to locate such documentation later. The time to document the backup to your claim is when you are on site, when the details are fresh in your mind and when the men and required information are readily available.It is also very important to respond to any suggestion that your work is incomplete or deficient, particularly as a project draws to a close. This is because, firstly, it is towards the end of the job that the owner and its consultant will generally issue deficiency lists. Also, it is to common for a party who has run out of money on a project to issue somewhat dubious lists of deficiencies and incomplete work as a basis for non-payment. In addition, allegations of delay may be made as a way to offset your claim. These should also be responded to.
Claimants should also understand the difference between, and keep separate, correspondence which puts your factual position on the record and correspondence with sets out your position on settlement. This is because if the two are combined, any suggestion that you might take less might be admissible in a trial and taken as an admission that your claim is not as strong as you say it is. Settlement proposals should be sent separately, and be clearly marked “without prejudice” so that the letters will not be admissible in evidence.
Avoid litigation when possible
We would also suggest that settlement possibilities be explored at an early stage. This is because, unfortunately, litigation can be very expensive and time consuming. If the lawyers are to be involved, however, (and depending on the amounts in issue) they should be brought in at an early stage to help protect your position and to ensure that all possible options are explored, including information requests potentially available under construction lien legislation, mediation or arbitration, bond claims, lien claims, trust actions and other legal proceedings. Your lawyer, if experienced in construction matters, should also be able to assist you, as required, to draft letters in response to allegations of delay or of deficient and incomplete work made by the other side.In the end, it is easy to focus on getting the job done, leaving debt collection issues to be dealt with later. Yet contractors, subcontractors and suppliers who take steps to manage debt collection throughout the life of a project will generally find themselves in a better position to collect at the end of the day.
Robert Kennaley is a former Landscape Design Build Contractor and an Honorary Member of Landscape Ontario who now practices construction law in Toronto and Simcoe, Ont. He can be reached at 416-368-2522 or at kennaley@mclauchlin.ca. This material is for information purposes and is not intended to provide legal advice. Readers who have concerns about any particular circumstance are encouraged to seek independent legal advice in that regard.